By Feb 22 they had the polystyrene boxes in place and the steel reinforcement for the concrete slab. This is the view looking North over the back bedrooms towards the garage.
This is the view looking West towards some of the other buildings that are going up. In the foreground is the front veranda and our bedroom.
On Sat 7th Feb 2009 we stepped out of the car into 47 degree obscene heat with a 60 Knot North wind blowing, but we didn't mind as the foundations had been dug out- A year since we signed the initial contract.
By Sat 14th Feb, smoke from the bush fires was still in the air, but they had laid the plumbing. Hopefully the slab will be there by next week.